Romanian Public Road Authority Claims EUR40M In Penalties From Contractors

Romania's public road authority CNADNR claimed penalties of about EUR40 million, between September 2010 and March 2011, from nine domestic and foreign companies, including Colas, FCC Construccion and Astaldi, for various violations.
Romanian Public Road Authority Claims EUR40M In Penalties From Contractors

Colas (France), which was contracted to build the Cernavoda-Medgidia highway segment, was ordered to pay EUR16.08 million as penalties for failing to expropriate land and delays in designing an alternative route and obtaining construction authorization, the Transport Ministry said in a press release. The ministry terminated the contract with Colas over these problems.

The FCC Construccion-Astaldi (Spain-Italy) consortium, working on the Constanta beltway, is liable for EUR12.38 million for „utility relocation, requiring additional land.”

FCC, in consortium with German firm Porr Technobau, has been asked by CNADNR to pay EUR1.59 million for delays in the design and construction of the Arad beltway.

CNADNR claims EUR8.23 million from the Egis Route-Egis BCEOM partnership, working on the Timisoara-Arad highway segment, for problems with the construction plan, changing the project without the authority’s permission, lack of utility identification in the auction papers, errors in cadastre documentation.

The authority said Astaldi, which is working on the national road between Arad and Oradea, has received a deposit it could not justify through work completed by the end of 2009 and has been ordered to pay penalties of EUR1.5 million.

The Carena-Tunele Brasov partnership, which is overdue on its work on a bridge, is asked to pay EUR13,458.

Other companies liable for more than EUR10,000 are Egis Romania and WSP Sweden.

The ministry also mentions EUR2.15 million won in arbitrage from Secol, over a contract to restore national road DN65 and certain projects financed by the International Bank for Reconstruction and Development.

Recomandarea video

Procurorul CSM Claudiu Sandu despre zborul cu jet privat al judecătorului CCR Cristian Deliorga: ”Cum se face că nu vedem nici o acțiune a Inspecției Judiciare? Există magistrați care își doresc lux și opulență, iar pentru asta sunt pregătiți să renunțe la imparțialitate”
G4Media
„Sucul-minune” a ajuns și în Premier League: de ce a devenit atât de căutată băutura care se găsește și la supermarket
GSP.ro
Scandalurile de corupție se țin lanț în Ucraina. O nouă demisie zguduie regimul lui Zelenski. Procurorul general s-a retras din funcție. Gândul face retrospectiva celor mai răsunatoare scandaluri de la începutul războiului
Gandul
Înmormântarea lui Costeluș de la Clejani, amânată pe termen nedeterminat? Scandal la INML, cu intervenția autorităților
Cancan
Imaginile cu Victoria au făcut furori pe net. Fosta soție a apărut în bikini
Prosport
O hotărâre CJUE din cazul unui primar PSD i-ar putea salva mandatul lui Fritz. Avocatul Tudor Chiuariu, care a obținut decizia: „Este valabilă și foarte actuală”
Libertatea
Ce problemă de sănătate are What’s Up: „Trăiesc aşa de 28 de ani, aşa m-am născut, sunt împăcat cu această idee”! Artistul participă la „Asia Express” alături de soția lui, Micky
CSID
Noua Dacia Spring nu va mai fi produsă în China. Unde se mută producția, dar nu în România
Promotor
Economia României frânează: PIB-ul stagnează în T2, iar industria se contractă puternic. Construcțiile și investițiile compensează scăderile
Economedia